Implementation and wiring

                                             

The Tyness and the card must be powered down.
Attention:
If the card is to be connected to a PME-PMI meter, the right terminal block must be used and the selection jumper must be placed on the PME-PMI side.
The card must be installed on the connectors of the EXT.1 or EXT.2 slots of the Tyness
The input wires must be inserted into the terminal blocks as shown below.

In order to remove a wire, you must first insert a fine tool into the opening above the wire as shown below. This will release the wire.

Wiring of the RJ45 TIC cable of an Enedis meter

Pins 4 and 6 must be used. The Enedis meters are not polarized except for the SME-SMI meters.

In this case:
Pin 4 must be connected to GND
Pin 6 must be connected to TX